Choose between a residual virtual submeter, a group total from several physical meters, and an analysis-only virtual meter.
The term virtual meter is used for several different configurations. Choose the option based on the electrical question you need to answer.
| Situation | Correct option | Result |
|---|---|---|
| Two or more physical meters together represent one shared electrical boundary | Aggregate the meters in an advanced group | The switchboard total is the sum of its meter members. |
| A real meter covers a switchboard, but one part has no submeter | Add a virtual energy submeter | The controller calculates the unmetered remainder. |
| You want to add or subtract arbitrary historical signals | Create a SmartgridX virtual meter | A calculated chart and CSV series, not a controller input. |
| Each grid connection has its own contractual or physical limit | Keep separate control boundaries | Each connection can be protected independently. |
Do not aggregate independent grid connections merely to obtain one convenient number. A safe total can hide an overload on one transformer, feeder, or connection. Aggregate only when the sum is the actual agreed control boundary, and preserve every individual equipment limit.
Use this topology when several measured feeders together form one common control boundary. Typical examples are two transformer feeders behind one shared site limit, or several departures whose powers must be summed for curtailment.
Meter A ──┐
├── Shared switchboard total = Meter A + Meter B
Meter B ──┘
An energy meter that is assigned to a device or group has a different meaning: it measures that entire child branch. Do not also add the same electrical flow elsewhere in the group tree, because it will be counted twice.
Meters may arrive through different supported communication routes, but every source must be timely and stable enough for the chosen control mode. A delayed or missing meter makes the aggregate an incomplete view of the boundary.
Keep the hierarchy faithful to the electrical installation:
For complex multi-transformer sites, validate the proposed single-line diagram and failure behaviour during commissioning before enabling automatic curtailment.
A virtual energy submeter estimates the part below one real meter that is not covered by its other measured children.
Virtual remainder = Real parent meter - all other known child branches
For example, a main meter measures a complete switchboard and a branch meter measures the EV chargers. The virtual submeter can represent everything else on that switchboard.
The controller creates a meter named after the measured branch with remaining energy (virtual meter) appended.
For arbitrary sums, differences, and scale factors in charts, use Virtual meters in SmartgridX Monitoring.
That function is well suited to questions such as:
Transformer total = Meter A + Meter B;Unmetered load = Main meter - Submeter A - Submeter B;It does not change the controller configuration and cannot be used as a setpoint or grid-control meter.
| Check | Verify before enabling control |
|---|---|
| Communication | Every physical meter is supported and reports reliably. |
| Direction | Import and export are confirmed with a known site event. |
| Scaling | Units, phase configuration, CT ratios, and scaling are correct. |
| Topology | The group tree matches the current single-line diagram. |
| No double counting | Every electrical flow occurs only once in the aggregate. |
| Limits | Shared and individual transformer, feeder, and grid limits are configured separately. |
| Fallback | Loss of one meter has an agreed safe operating response. |
| Validation | The calculated total is compared with a trusted reference. |
See Grouping devices for the advanced group editor and Supported energy meters for device-specific wiring and setup.