Currently, the integration is support upto a state of charge limit to 95%. This is because when the state of charge goes beyond 95%, the battery can stop listening to setpoints due to the actions of the battery management system. We are working on resolving this issue with Dyness and other partners.
In beta and available on request. The additions in this overview require the matching integration or controller update and are not confirmed as part of the standard customer release. Request them through your existing Eniris support conversation. The status applies to these additions, not to every existing function of the devices listed elsewhere on this page.
| Model family | Connection | Beta addition | Validation and conditions |
|---|---|---|---|
| LS (including D5.0K-LS) | RS485 or Modbus TCP | In beta and available on request: corrected inverter phase-current readings | Protocol V1.16 mapping and offline regression verified; installation and physical validation pending |
| HT-A | RS485 or Modbus TCP | In beta and available on request: corrected inverter phase-current readings | Shared protocol mapping verified offline; this family has not been physically validated for this correction |
This targeted update reads inverter phase currents from the protocol's current registers rather than its grid-frequency registers. Existing power, voltage and control mappings are retained. It does not repair interruptions in a separate P1 meter connection or restore missing historical measurements. Installation requires an agreed execution window and verification on the actual system.
| Model / system | Beta addition | Validation and conditions |
|---|---|---|
| Dyness DH800Y | Cabinet implementation candidate | Technical assessment and physical commissioning required |
| Model | Connection | Beta addition | Validation and conditions |
|---|---|---|---|
| DH200Y, 100 kW / 232 kWh | Modbus TCP | In beta and available on request: dedicated V7.1 custom driver | Engine validation and 18 simulated command cases passed. Installed and readout verified on one cabinet on 10 November 2026; a 4 kW charging request produced approximately 3.6-3.8 kW at the battery. Physical discharge validation remains pending because low-state-of-charge protection held the discharge request at zero. |
The dedicated driver preserves battery and inverter measurements, maps operating mode 4 to Remote, and includes the remote communication fault. It leaves reserved holding registers 140, 706 and 707 untouched and never writes the cabinet on/off register 700. Requests at or below 1 kW become zero. Larger requests retain their requested value within the live BMS power/current permissions and the cabinet rating. BMS bits 0, 1 and 6 must grant the corresponding charge, discharge and PCS permissions; controller state-of-charge protections remain active. PV curtailment is not available through this DH200Y V7.1 map. A compatible custom-driver engine and an agreed installation window are required. The DH200Y C260 / DH261Y uses a different protocol and is not covered by this definition.
| Model / system | Beta addition | Validation and conditions |
|---|---|---|
| Dyness DH-series EMS | Separate EMS implementation candidate | Match actual cabinet protocol; physical commissioning required |
See integration details for connection requirements and operating limitations.
| Device Type | Variants | Modbus TCP (Ethernet) | RS485 | Curtailment | Reactive power control | Instruction video |
|---|---|---|---|---|---|---|
| EC100 | 100kWh | ✅ | ✅ | ✅ | — | — |
| DH100F | 71~100kWh | |||||
| DH200F | 100kW/215kWh | — | ||||
| DH200Y | 100kW/232kWh | ❌ | — | |||
| LS | ✅ | |||||
| HT-A | ||||||
| DH800Y | ❌ | — |
| Model family | Modbus TCP port | RS485 settings | Modbus address range |
|---|---|---|---|
| LS and HT-A | 502 | 9600 baud, 8N1 | 1–247 |
| DH800Y | 502 | 115200 baud, 8N1 | 1–99 |
LS and HT-A are separate choices in the device wizard. Select the model installed on site rather than using a DH100F profile.
The DH800Y connection requires controller software that includes it and is currently available in the testing software line. Its presence on this page does not mean every installed controller already offers it.
DH800Y supports a battery AC power setpoint and battery-cluster, state-of-charge, energy and alarm readings. A PV power reading does not provide separate PV curtailment: that command is not available through this integration.
Before controlling a DH800Y, open its HMI or web interface and set Control mode → Remote mode. The controller does not enable this setting automatically.
The SmartgridOne Controller and the Dyness inverters communicate via RS485 or Ethernet.
For correct ethernet wiring: Follow the the guidelines for ethernet wiring.
The COM6 wiring example below belongs to the cabinet-style connection. Do not reuse it as an LS or HT-A terminal diagram; use the RS485 terminal markings in the manual for that model.
| Device | SmartgridOne Controller model OM1 | SmartgridOne Controller model IG8 | RS485-USB converter | RS485-Ethernet converter |
|---|---|---|---|---|
| COM6 terminal 1A | RS485 A | RS485_POS | RS485 A | TX+ |
| Com6 terminal 1B | RS485 B | RS485_NEG | RS485 B | TX- |
| N/A | RS GND | GND | Not available | G |
The Dyness DH100F needs to be set to remote mode:
An earlier implemented candidate remains available for technical assessment on request. Its earlier review was closed; Eniris must review and prepare the appropriate version before installation. It is not a ready-to-install standard release. Separate implementation candidates exist for DH800Y and DH-series EMS. Their interface and battery-control behaviour must be matched to the actual cabinet and commissioned; they are not interchangeable merely because both are Dyness systems.